Week of 7/20/2020 – Contractor to begin mobilization to the site
Week of 7/27/2020 – Transition to alternating one-lane travel
Week of 8/3/2020 – Cofferdam installation (All boating traffic ceases)
Week of 9/10/2020 – Completion of first half (alternating one-lane travel switches lanes)
Week of 11/3/2020 – Estimated date of project completion

Any changes will be updated on this page as they are received.